REQUIRED TOOLS

  • Screwdrive T25 Torx head
  • Allen key #5



REQUIRED PARTS



BEFORE YOU START



PROCEDURE

  • Switch on the Perfect Moose Jack.
  • Overrule the heating phase by pressing slightly on the pitcher holder. Perform the 'Big boiler flush'

  • Press on the 'Drain'-button.
    OR
    Release the pressure from the boiler by pressing on valve 4 'Flush', the heating element won't heat up the water as we have removed the HEAT-faston from the boiler. 

 
  • Unscrew the 2 screws from the base plate with an allen key #5 and 1 screw from the structure support and boiler support with a Torx T25 screwdriver. Now it is possible to remove the boiler unit from the Perfect Moose Jack. 
 

  • Reuse the 6mm pushfit fitting with 1/4" thread and the 8mm push elbow fitting with 1/4" thread. Screw both the fittings on the new drain valve with a max force of 3.5Nm and place back on the boiler.
  • Reconnect the 6mm hose on the boiler. Reconnect the drain valve on the boiler and T-piece with 6mm pushfit and 8mm stem.
  • Screw the 2 screws in the boiler support on the side of the boiler with an allen key #5.

  • Place the boiler unit back on the Perfect Moose Jack. Screw the 2 screws on the base plate with an allen key #5 and 1 screw on the structure support and boiler support with a Torx T25 screwdriver.
    Be careful to not squash the cables between the boiler support and structure support.